We are interested in implementing ISO 27001 but we have some interrogations on how much time it takes. Your solution with a tool kit is a very good option because it is cheaper than a consultant and we can't imagine going on the ISO journey alone!
During the webinar, you said that for a small organization (we are 2 in the US for the strategic part + a development team of 3 people in India) it can take between 5 and 8 months to implement ISO 27001. Can you tell me in this case with your tool kit how much time do you think the project leader should work on ISO during his week?
Assign topic to the user
Expert
Rhand Leal
Nov 25, 2019
The time estimation for project duration considers a dedication of c.a. 20% work time, i.e., the project leader would work 1 day per week tops in the project.