Final Presentation of Project Results
In the Project Plan template, it has a place to enter a date for the Final Presentation of Project Results.
Who is this presentation to and should it be done before or after the self-audit?
Assign topic to the user
Please note that the project objective is "To implement the Information Security Management System in accordance with the ISO 27001 standard by [date] at the latest."
Considering that, the presentation is directed to the person which is responsible for the ISMS scope (e.g., the CEO if the ISMS scope covers all the organization, or the department head if the ISMS is restricted to a department).
As for when the presentation should be held, you should consider a time after the management review, so the persons held responsible for implementing the decisions taken in the management review have time to provide some details about how the decisions will be implemented.