Answer: ISO 27001 revision 2013 is based on PDCA (Plan-Do-Check-Act) cycle, even though this fact was not emphasized in the introduction.
This is visible when you look at the main clauses of ISO 27001:2013:
- 4 Context of the organization - Plan phase
- 5 Leadership - Plan phase
- 6 Planning - Plan phase
- 7 Support - Plan phase
- 8 Operation - Do phase
- 9 Performance evaluation - Check phase
- 10 Improvement - Act phase