Is ISO 27001:2013 based on PDCA cycle?

  Quote
Guest
Guest user Created:   Jan 12, 2016 Last commented:   Jan 12, 2016

Is ISO 27001:2013 based on PDCA cycle?

I have one doubt in ISO 27001. Is ISO 27001:2013 based on PDCA cycle? If not what is the new approach.
0 0

Assign topic to the user

ISO 27001 DOCUMENTATION TOOLKIT

Step-by-step implementation for smaller companies.

ISO 27001 DOCUMENTATION TOOLKIT

Step-by-step implementation for smaller companies.

Guest
DejanK Jan 12, 2016

Answer: ISO 27001 revision 2013 is based on PDCA (Plan-Do-Check-Act) cycle, even though this fact was not emphasized in the introduction.

This is visible when you look at the main clauses of ISO 27001:2013:
- 4 Context of the organization - Plan phase
- 5 Leadership - Plan phase
- 6 Planning - Plan phase
- 7 Support - Plan phase
- 8 Operation - Do phase
- 9 Performance evaluation - Check phase
- 10 Improvement - Act phase