industrialization KPI's

  Quote
Guest
SAFA Created:   Jan 05, 2021 Last commented:   Jan 08, 2021

industrialization KPI's

Hello,
Happy new year everyone!

i'm wondering what indicators which commonly used to mesure the performance of the industrialization process which includes APQP procedure and the PPAP file submission

thank you for your help!

best regards

0 0

Assign topic to the user

IATF 16949 DOCUMENTATION TOOLKIT

Step-by-step implementation for smaller companies.

IATF 16949 DOCUMENTATION TOOLKIT

Step-by-step implementation for smaller companies.

Expert
Fırat İnceli Jan 06, 2021

Usually, the following key process indicators can be used. For example.

  • Compliance rate with the project plan
  • First time approved PPAP rate
  • PPAP rate given on time
  • Number of complaints received during the APQP phase

For more informaion, see:

Quote
0 1
Guest
SAFA Jan 06, 2021

Hello,

thanks for replying

but the are efficiency indicators right ?

Quote
0 0
Expert
Fırat İnceli Jan 07, 2021

Efficiency targets are relted to the organization; effectiveness targets  are related to the customer. For example; As the goal of delivering customer projects on time is related to the customer; is the goal of effectiveness. Regarding the compliance with the project budget at the project stage or by a target organization, the amount of scrap not exceeding 1%, the goal is efficiency. It is not very important whether it is efficiency or efficiency goal, but it is an important detail to set a target that will satisfy the customer and the institution and provide added value.

Quote
0 1
Guest
SAFA Jan 07, 2021

Hello,

thank you for clarifications
i want to calculate the cost of the planning phase and fix a target value not to be exceeded. how can I calculate this cost it seems ambiguous to me
the planning phase is the APQP phases except the product conception and developpement one plus the preparation of the PPAP level 3 file
have you some recommandations please?

Quote
0 0
Expert
Fırat İnceli Jan 08, 2021

You can set a project implementation budget target and look at the realization rate of this budget. The project implementation budget target should be set on an individual project basis. The project budget should be determined on a project basis. When you define the project budget,   you should take into consideration of; 

- Number of the tool to be made, 

 -the new machine to be taken cost, 

- the number of samples to be made, 

- investment cost, 

- Product validation, test cost 

- New test machine investment 

- travel cost to customer or supplier site, 

- supplier investments,  

- etc.

 

 

Quote
0 0