ISO 22301 toolkit content relate to internal and external issues

  Quote
Guest
Guest user Created:   Nov 13, 2017 Last commented:   Nov 13, 2017

ISO 22301 toolkit content relate to internal and external issues

I have read the toolkit documentation and I have noticed that documentation does not address the internal and external issues in relation with the context of the organization. May I have something on that.
0 0

Assign topic to the user

ISO 27001 DOCUMENTATION TOOLKIT

Step-by-step implementation for smaller companies.

ISO 27001 DOCUMENTATION TOOLKIT

Step-by-step implementation for smaller companies.

Expert
Rhand Leal Nov 13, 2017

Answer: The information required by ISO 22301 clause 4.1 is addressed by following templates:
- Organization's activities (from clause 4.1 a)) and potential impact from disruptive incidents are addressed by template Business Impact Analysis Questionnaire (located at folder 04 Business Impact Analysis Methodology)
- Organization's functions (from clause 4.1 a)) are addressed in all templates when an activity to be performed is required (by means of the field [job title]). Functions related specifically to the BCMS are defined in the template Business Continuity Policy, section 3.5, (located at folder 03 Business Continuity Policy)
- Organization's product and services (from clause 4.1 a)) are addressed by template Business Continuity Policy, section 3.5, (located at folder 03 Business Continuity Policy)
- Relations with suppliers, partners and interested parties (from clause 4.1 a)) are addressed by template Business Continuity Strategy (located at folder 05 Business Continuity Strategy)
- Relationships between the Business Continuity Policy and other organization's policies, objectives and general risk management strategy (from clause 4.1 b)) are addressed by template Business Continuity Policy, section 2, (located at folder 03 Business Continuity Policy)
- Organization's risk appetite (from clause 4.1 c)) is addressed by template Business Impact Analysis Questionnaire, section 6 (maximum acceptable outage) (located at folder 04 Business Impact Analysis Methodology)