Quick question on the timescales for treatment and the plan. We have identified the activities that need to be completed and put into the plan. Is the timescale for these remediation points the timescale that we are working towards for risk treatment?
0 0

Assign topic to the user

ISO 27001 RISK TREATMENT PLAN

Determine responsibilities for the implementation of controls.

ISO 27001 RISK TREATMENT PLAN

Determine responsibilities for the implementation of controls.

Expert
Rhand Leal Jan 24, 2017

Answer: Yes, the time you need to complete for each of these activities, and the sequences and dependencies that exist between them, will provide you the information about the total time required for risk treatment completion.

In the video tutorials that came with your toolkit, you will see information on how to fill out all the data about the risk treatment plan.

Quote
0 0

Comment as guest or Sign in

HTML tags are not allowed

Jan 24, 2017

Jan 24, 2017

Suggested Topics