I would like to know what would be on a list of deliverables for an NPI project in an IATF-certified organization
Assign topic to the user
Expert
Fırat İnceli
Aug 29, 2023
In the new product introduction process (NPI), you should comply with the requirements of clause 8.3 of the IATF 16949:2016 standard. All requests on this subject are specified in sub-items 8.3 and 8.3.
I have listed a few conditions that should be followed on this subject below, but I recommend that you review these relevant articles in detail.
- If you are designing products, design FMEA
- Process FMEA
- Control Plan
- Project Plan
- Feasibility analysis
- Design validity test plan and tests
- Prototype control plan
- Product and process validation records
- MSA and SPC studies
- All PPAP requests
- Customer-specific requirements about it, etc.