Is a PDCA Cycle a requirement of AS9100D? Do I have to do a PDCA and document?
Assign topic to the user
Expert
Mark Hammar
Feb 20, 2019
Answer:
No, you do not need to do a PDCA document for AS9100 Rev D. The plan-do-check-act cycle is par of the standard, as referenced in the diagram at the start of the standard, but there is no requirement to have a PDCA process or to document it.
To better understand how PDCA works in AS9100 Rev D, see this article:
PDCA cycle in AS9100 Rev D, https://advisera.com/9100academy/knowledgebase/pdca-cycle-in-as9100-rev-d/