Standard change
Assign topic to the user
Answer:
There are (many) different kinds of changes which are considered as standard change. Usually, each one of them has separate procedure how to fulfill them. In order to have efficient Standard Change Management process in place, you need to have following:
1. clearly defined procedure - usually defined by Change Manager or someone from Technical Management. This also includes triggers i.e. how to initiate that procedure (and who is allowed to do that)
2. Responsibilities - i.e. who is doing what
3. clearly communicated procedure to all relevant/involved parties
Following article can help you with this issue:
"Tips and tricks for using the ITIL standard change mechanism" https://advisera.com/20000academy/blog/2017/06/27/tips-and-tricks-for-using-the-itil-standard-change-mechanism/